Fee Road ,Wilson Road Construction Project Notice

Where: Wilson Road, Fee Road, East Shaw Lane, South Hagadorn Road, Parking Lot 30, Parking Lot 31, Parking Lot 32, Parking Lot 33, and the Conrad Hall Loop

When: Commencing on Monday, March 5, 2018, with scheduled completion on Thursday, November 15, 2018

What is being done: Commencement of work on the project: CP11349 - Roads - Wilson Road Extension. The scope of the project will include: removal and replacement of concrete/bituminous pavement and parking lots, storm sewers, water mains, traffic signals, landscaping, lighting, pavement markings, signage, miscellaneous site amenities, and related work.  Please see attached graphic.

Why this is being done: To extend Wilson Road to Hagadorn Road with a signalized intersection.

How this will impact the campus community: There will be vehicle and pedestrian detours around the work site during this work as well as intermittent construction noise and dust.

Who to contact for more information: Andy Linebaugh, project representative, at (517) 432-7103 or alinebau@ipf.msu.edu, or IPF at (517) 353-1760.

  • Maps can be found at: 

http://ipf.msu.edu/_files/docs/DOC022118-02212018153237.pdf

http://ipf.msu.edu/_files/docs/DOC022118-02212018153245.pdf

MSU Infrastructure Planning and Facilities builds and maintains the physical environment for Michigan State University’s education, research and outreach missions, and directs the university’s sustainability initiatives and long-term infrastructure planning goals. The unit’s experienced team of professionals keeps MSU running 24/7/365, delivering an immense menu of services and providing expert analysis for university objectives. Visit the MSU IPF website for additional information, or call (517) 353-1760 for IPF questions or to report an issue or emergency.